二112160胶带顺槽大坡度改造施工方案

(整期优先)网络出版时间:2022-04-26
/ 1

二 112160胶带顺槽大坡度改造施工方案

薛坤

洛阳义安矿业有限公司


摘要:112160胶带顺槽为沿空掘巷,根据原12150轨道顺槽地质资料,胶带顺槽沿二1顶板掘进,致使胶带顺槽出现100米长低洼点25°上坡,巷道掘进期间根据实际探煤资料煤层分叉,岩柱3-12米见煤,煤厚3-9米,后期考虑皮带运输及工作面安装,对胶带顺槽100米大坡度段进行改造。

Luoyang Yi 'an Mining Co., LTD. (xuekun)

Abstract: II 112160 belt trench is excavated along the goaf. According to the geological data of the original 12150 track trench, the belt trench is excavated along the II 1 roof, resulting in a 100 meter long low-lying point 25 ° uphill. During the roadway excavation, according to the actual coal exploration data, the coal seam is forked, the rock pillar is 3-12 meters, the coal is 3-9 meters thick, and the belt transportation and working face installation are considered in the later stage, Reconstruct the 100m large slope section of the belt along the groove.

关键词:沿空掘巷;大坡度;巷道改造;

1 工程概况

原12160胶带顺槽设计长度1026米,根据原12150轨道顺槽煤层位置为 ,通过沿空掘巷,低洼点煤层位置为标高-180- -270,工作面安装运输路线为西轨大巷-12160中车场-西胶带大巷-12160胶带顺槽-切眼,为保证工作面安装及后期回采出煤,对12160胶带顺槽25°坡进行改造为5°。

2 改造方案

112160胶带顺槽6Y11'点方位315°坡度+5°施工98.58m。

62675d0dbdece_html_90b8dcafd60580e3.png

36U型棚断面支护设计:采用36U型钢棚支护,净宽5964mm,净高3932mm,36U型钢棚为4节棚,梁长3400mm、腿长3300mm,棚距700mm,S净=19m2,S掘=20.7m2

改造巷道全断面从外往里依次采用小圆木+塑料网进行裱褙,帮部使用双层荆芭背设,小圆木长1700mm,紧贴36U型钢棚进行背设,净间距300mm,交错背设;塑料网对接,孔孔必连每隔200mm打一个死结,空帮、空顶部分用煤袋进行充填,要求靠帮接顶,背牢背实。

开口顶板较破碎时采用木钎子或管缝锚杆超前控顶。

3 实施过程

在二112160胶带顺槽低洼处顺坡改造点前后岩柱2m的位置正中打设木垛加固,木垛使用2.4*4m规格的木垛加固横向长2.4m长圆木,掘进方向4m长圆木。两头的木垛紧挨打设,中间木垛每3m一架,圆木与圆木层之间使用扒钉固定,要求接顶背牢背实。

112160胶带顺槽低洼处顺坡改造6Y11'点处的36U型钢棚拆除共计11.83m,拆棚段巷道底板使用煤袋充填。

开口加固支护:施工前巷道口打设木垛加固→敲帮问顶→对套棚段36U型棚进行超前加固→拆除套棚段顶部煤袋→拆除开口段36U型棚→木垛空隙使用煤袋进行添堵→检查套棚前36U型棚支护情况→打设临时支护加固→依次循环36U型钢套棚段拆除完毕。

托煤、过煤段、顶板破碎时:采用3根前探梁+管缝锚杆(或木钎子)超前支护。

4改造效果

巷道改造后,低洼点坡度由原25°改为5°坡,恢复运输系统后,安装无极绳绞车,使工作面安装顺利进行。后期工作面回采释放煤量15万吨,效益

7200万元。