金川水电站导流洞进口爆破振动控制和监测

(整期优先)网络出版时间:2023-02-14
/ 5

金川水电站导流洞进口爆破振动控制和监测

唐浩杰

(中国安能集团第一工程局有限公司, 广西南宁 530028)

摘要:针对金川水电站导流洞进口边坡地质条件差和高陡边坡对爆破振动敏感的特点,使用数码电子雷管和逐孔起爆技术控制爆破振动峰值,严格执行“先坡后洞”的设计理念,通过质点振动速度、锚索应力计、多点位移计和表观测量等监测手段,及时掌握质点振动速度峰值和边坡位移变形情况,确保了边坡安全稳定,也为川西地区类似地质条件的边坡基坑开挖施工提供借鉴。

关键词:先坡后洞;数码电子雷管;逐孔起爆;表观测量;质点振动速度;锚索测力计;多点位移计。

Control and monitoring of blasting vibration at inlet of persion tunnel of Jinchuan Hydropower Station

TANG Haojie

(China Anneng Group First Engineering Bureau Co., Ltd., Nanning, Guangxi 530028)

Abstract: In view of the poor geological conditions of the inlet slope of the persion tunnel of Jinchuan Hydropower Station and the sensitivity of the high and steep slope to blasting vibration,The digital electronic detonator and hole by hole initiation technology are used to control the blasting vibration peak,Strictly implement the design concept of "slope before tunnel",Through monitoring means such as particle vibration velocity, anchor cable stress meter, multi-point displacement meter and apparent measurement,Timely grasp the peak value of particle vibration velocity and slope displacement and deformation,Ensure the safety and stability of the slope,It also provides a reference for the excavation and construction of slope foundation pit with similar geological conditions in Western Sichuan.

Key words: Slope before hole;Digital electronic detonator;Hole by hole initiation;Apparent measurement;Particle velocity;Anchor cable dynamometer;Multipoint Displacement Meter.

1  工程概述

1.1 工程简述

金川水电站位于四川省阿坝州金川县境内的大渡河上游河段,是大渡河干流规划的第6个梯级电站,其上游为双江口水电站、下游为安宁水电站,电站装机容量为900MW。金川水电站为二等大(2)型工程,枢纽工程主要由混凝土面板堆石坝、左岸引水发电系统、右岸溢洪道及生态泄水道和泄洪洞等建筑物组成。

导流洞布置在右岸,断面型式为城门洞型,按有压洞设计,过水断面尺寸为12.5m×14.5m(宽×高),进口底板高程为2155.0m,洞身长1035.75m,纵坡i=4.92‰。导流洞进口开挖支护包括进口边坡、进水塔基坑和导流洞渐变段(岩塞段,长20m)三个部位。

导流洞进口边坡共设置3级开挖边坡,开口线外上方还有原始坡面进行锚索支护,马道高程分别为2221、2201m,设计坡比为1:0.33,高程2175m以下为垂直边坡,开挖边坡总高度为84m;高程2165m以下为导流洞进水塔基坑,基坑开挖尺寸为长26m×宽24m×深13m。进水塔后渐变段桩号为导0+000~导0+020,由矩形渐变为城门洞型,设计开挖断面宽16.9 m×高20.24~ 18.70m。

1.2工程地质

导流洞进口岩石岩性为三叠系薄~厚层状变质细砂岩夹碳质千枚岩,岩层产状NW 310°~320°SW∠50°~55°,属于陡倾角。整个导流洞进口岩体属于Bxt2倾倒变形体,进水口边坡高陡,岩体深卸荷,岩层裂隙发育,岩石破碎,并位于Bxt2倾倒变形体下方,对爆破振动敏感。

1.3开挖支护设计理念

边坡开挖理念:少挖强支护、“先坡后洞”,因为整个边坡位于Bxt2倾倒变形体,岩体陡倾角,边坡一经开挖、扰动就很容易引起上方边坡的变形、塌方,所以边坡采取开挖少挖强支护、先开挖形成边坡并支护完成再进洞(渐变段,也叫岩塞段)的方法。

边坡支护理念:随挖随支护,开挖一段就支护一段,岩石岩性、产状、岩层裂隙发育和岩石破碎等地质条件决定了边坡需随挖随支护(包括锚索等深层支护),开挖一段就支护一段,否则极易引起边坡的变形和塌方。

2爆破振动安全允许标准

《爆破安全规程》(GB6722-2014)、《水工建筑物岩石基础开挖工程施工技术规范》(DL/T5389-2007)等规程规范都对爆破振动安全允许标准进行了规定,下表为《爆破安全规程》(GB6722-2014)中对爆破振动安全允许标准规定值。

表2-1    爆破振动安全允许标准

序号

保护对象类别

安全允许质点振动速度Vcm/s

f10Hz

10Hf50Hz

f50Hz

1

土窑洞、土坯房、毛石房屋

0.15~0.45

0.45~0.9

0.9~1.5

2

一般民用建筑物

1.5~2.0

2.0~2.5

2.5~3.0

3

工业和商业建筑物

2.5~3.5

3.5~4.5

4.2~5.0

4

一般古建筑与古迹

0.1~0.2

0.2~0.3

0.3~0.5

5

运行中的水电站及发电厂中心控制室设备

0.5~0.6

0.6~0.7

0.7~0.9

6

水工隧洞

7~8

8~10

10~15

7

交通隧洞

10~12

12~25

15~20

8

矿山巷道

15~18

18~25

20~30

9

永久性岩石高边坡

5~9

8~12

10~15

10

新浇大体积混凝土(C20):                                            龄期:初凝~3天                                                               龄期:3天~7天                                                                 龄期:7天~28天

1.5~2.0                                              3.0~4.0                                  7.0~8.0

2.0~2.5                                    4.0~5.0                        8.0~10.0

2.5~3.0                                                 5.0~7.0                                    10.0~12

      爆破振动监测应同时测定质点振动相互垂直的三个分量。
      注: 1:表中质点振动速度为三个分量中的最大值,振动频率为主振频率。
           2:频率范围根据现场实测波形确定或按如下数据选取:硐室爆破f小于20Hz,露天深孔爆破f在10Hz~60Hz之间,露天浅孔爆破f在40Hz~100Hz之间;地下深孔爆破30Hz~100Hz之间;地下浅孔爆破f在60Hz~300Hz之间。       

在实际施工过程中,因岩石地质情况等多种因素,往往V的取值比允许标准值还要小,以确保边坡和周边建筑物的安全稳定。

3规范允许的段最大装药量

爆破工程施工常常采用萨道夫斯基经验公式:v=k(Q^(1/3)/R)^α对质点振动速度V值进行计算,由公式可知当通过多次爆破试验采用线性回归得出a、k值时,质点的振动速度V就与Q、R值成一定的比例关系,最大段装药量Q越大,V值就相应增大,爆破振动就越大,对保护对象产生的危害就越大,因此在总结大量经验数据的基础上,相关的规程规范对最大段装药量给出了限制,如《水工建筑物岩石基础开挖工程施工技术规范》(DL/T5389-2007)规定:

   8.4.4 预裂爆破或光面爆破的最大一段起爆药量,不宜大于50kg。

   8.5.3 台阶爆破的最大一段起爆药量,应不大于300kg;邻近设计建基面和设计边坡的台阶爆破以及缓冲孔爆破的最大一段起爆药量,应不大于100kg。

在实际施工过程中,因岩石地质情况等多种因素,往往单响药量(段装药量)的取值比允许段最大装药量还要小,以降低V值,确保边坡和周边建筑物的安全稳定。

4  导流洞进口开挖

爆破器材:数码电子雷管、2#岩石乳化炸药(φ32、70)、导爆索。

4.1 边坡开挖

第一级边坡山体很薄,只有一排预裂孔和几个缓冲孔,预裂爆破开挖。

第二级边坡山体较薄,只有一排预裂孔和几个主爆孔,预裂爆破+液压反铲破碎锤开挖。

第三级边坡:液压反铲破碎锤(边坡塌方后不允许爆破开挖)。

预裂爆破参数:孔径φ90,孔距80cm,不耦合系数2.81,线装药密度:0.18~0.25 kg /m。

2021年7月20日,导流洞进口3级边坡全部开挖完成。

4.2 渐变段(岩塞段)开挖

渐变段(岩塞段):上层,光爆(循环进尺1m)+预留核心土;中层,光爆+拉槽逐孔起爆(单孔单响);下层,光爆+拉槽逐孔起爆。

渐变段中、下层拉槽开挖爆破参数:单孔单响,孔装药量8~14kg,孔间延时100ms,单耗0.36~0.42 kg /m3

光爆孔线装药密度:0.18~0.22 kg /m。

4.3 进水塔基坑开挖

开挖方法:预裂+逐孔起爆 。预裂爆破参数:孔径φ90,孔距80cm,不耦合系数2.81,线装药密度:0.22~0.30 kg /m;主爆孔孔间排距2.0 m /2.5 m×2.0 m,孔深5~6m,单孔单响,单响装药量8~12kg,孔间延时100ms,单耗0.35~0.4 kg /m3。

2021年8月22日,导流洞进口渐变段和基坑全部开挖完成。

5 边坡塌方

2020年12月26日,第二级边坡坡面素喷混凝土封闭后因岩石结构面原因塌方; 2021年3月10日和3月20日,开挖边坡开口线外下游侧原公路边坡山体塌方; 2021年5月10日,第三级边坡开挖到2171m高程时,开口线外下游侧原公路边坡山体塌方,进而拉裂已支护的边坡。第三级边坡都是开挖5m就支护(锚索)5m,完成后再往下开挖。

6质点振动速度计算

6.1 渐变段质点振动速度计算

根据《水电水利工程爆破安全监测规程》DL/T5333-2005,在同一高程,爆破质点振动速度传播规律,按下式进行回归整理: v=k(Q1/3/R)α

采用四川大学在导流洞上层爆破开挖多次监测、回归整理的各向破振动衰减规律(f值都大于50Hz):

水平径向振速衰减规律: v=57.6(Q1/3/R)1.6

水平切向振速衰减规律: v=82.2(Q1/3/R)1.56

垂直向振速衰减规律:   v=79.6(Q1/3/R)1.51

导流洞渐变段中层爆破时的V值计算:

Q取最大值14kg,R=8.5m(拱顶)、36m(二级边坡坡脚)

水平径向: v=57.6(Q1/3/R)1.6       7.67cm/s       0.76cm/s

水平切向: v=82.2(Q1/3/R)1.56     11.51cm/s       1.21cm/s    

垂直向:   v=79.6(Q1/3/R)1.51      11.87cm/s       1.34cm/s

爆破振动安全允许标准:10~15cm/s(f>50Hz)。

渐变段中、下层爆破最大段(孔)装药量为14kg,之后降为8kg。

6.2 进口基坑开挖质点振动速度计算

采用四川大学在导流洞进口边坡爆破开挖时多次监测、回归整理的各向爆破振动衰减规律(f值绝大部份在10~50Hz之间):

水平径向振速衰减规律: v=69.8(Q1/3/R)1.74

水平切向振速衰减规律: v=103.5(Q1/3/R)1.77

垂直向振速衰减规律:   v=70.2(Q1/3/R)1.87

导流洞进口基坑爆破时的V值计算:

Q取最大值12kg,R=11.88m(水平距离二级边坡坡脚)、37.9m(二级边坡坡脚)

水平径向v=69.8(Q1/3/R)1.74        3.98cm/s 0.53cm/s   

水平切向v=103.5(Q1/3/R)1.77       5.61cm/s            0.72cm/s

垂直向v=70.2(Q1/3/R)1.87         3.23cm/s            0.37cm/s 

爆破振动安全允许标准:8~12cm/s(10Hz<f≤50Hz)。 进口基坑单响(孔)最大装药量为12kg(只有一次),之后降为8kg。

7边坡安全监测

对爆破振动及开挖“切脚”后引起的边坡变形/位移问题,除了采用质点振动速度监测外,还采用表观监测棱镜、锚杆应力计、多点位移计和锚索测力计等监测仪器进行监测。

导流洞进口边坡(开口线外上方边坡、第一至第三级边坡共四级)安装有多套表观监测棱镜、锚杆应力计、多点位移计和 锚索测力计等监测仪器, 对边坡变形/位移进行监测。

2020年12月26日、2021年3月20日、2021年5月10日3次塌方,监测数据均发生突变增大,表明边坡发生较大变形/位移。

7.1 边坡表面变形观测

导流洞进口边坡设置了多个点的表观变形监测,其中点TP4-DLJ监测数据如下表所示。

表7-1      点TP4-DLJ监测简化数据表

观测日期

△X累计位移(mm)

△Y累计位移(mm)

△H累计位移(mm)

水平合位移(mm)

备注

2020/12/21

0.00

0.00

0.00

0.00

2020/12/26

2.80

1.80

0.70

3.33

发生塌方

2020/12/27

1.60

-0.40

5.90

1.65

2020/12/28

1.60

4.60

-0.70

4.87

2020/12/29

2.50

4.70

-0.30

5.32

2020/12/30

2.30

5.30

0.80

5.78

2021/1/2

1.20

4.60

0.20

4.75

2021/1/5

2.90

4.80

2.30

5.61

2021/1/13

4.90

7.00

-3.60

8.54

2021/1/19

5.50

8.70

-2.00

10.29

2021/1/27

8.80

13.30

-1.40

15.95

2021/2/2

10.70

15.20

-0.20

18.59

2021/2/8

12.40

17.10

0.10

21.12

2021/2/15

13.90

18.90

-0.10

23.46

2021/2/22

14.70

20.10

1.40

24.90

2021/2/26

10.50

19.00

0.50

21.71

2021/3/1

15.50

22.90

5.00

27.65

2021/3/5

15.80

24.80

7.10

29.41

2021/3/7

15.40

25.60

6.50

29.88

2021/3/9

17.60

26.30

7.80

31.65

2021/3/11

17.10

27.00

6.30

31.96

发生塌方

2021/3/12

27.50

53.90

23.90

60.51

2021/3/13

29.60

61.80

26.20

68.52

2021/3/14

31.70

64.80

29.40

72.14

2021/3/15

32.80

66.90

31.50

74.51

2021/3/16

35.10

70.40

33.00

78.66

2021/3/17

35.00

71.50

33.00

79.61

2021/3/18

34.60

72.30

35.80

80.15

2021/3/19

41.80

86.50

52.10

96.07

2021/3/20

46.40

93.50

52.70

104.38

发生塌方

2021/3/21

49.60

98.60

56.70

110.37

2021/3/22

67.70

131.40

80.20

147.81

2021/3/23

73.90

138.00

87.60

156.54

2021/3/24

74.80

139.70

87.10

158.46

2021/3/25

75.30

142.10

87.80

160.82

2021/3/26

76.60

143.40

88.30

162.58

2021/3/27

76.30

144.00

90.20

162.97

2021/3/28

77.20

145.80

91.30

164.98

2021/3/29

78.00

146.30

92.00

165.79

2021/3/30

80.10

148.70

93.50

168.90

2021/3/31

79.50

148.70

93.50

168.62

2021/4/1

80.90

149.50

92.90

169.99

2021/4/2

79.40

150.80

91.90

170.43

2021/4/5

83.00

151.70

97.60

172.92

2021/4/9

71.00

145.40

96.90

161.81

2021/4/12

82.10

151.60

95.80

172.40

2021/4/16

82.00

151.30

98.80

172.09

2021/4/19

82.10

153.20

94.80

173.81

2021/4/23

83.90

150.00

98.60

171.87

2021/4/26

80.20

152.30

100.10

172.13

2021/5/3

85.10

154.70

100.56

176.56

2021/5/10

83.04

158.90

100.27

179.29

发生塌方

2021/5/11

89.40

161.00

105.70

184.16

2021/5/12

89.40

163.70

109.80

186.52

2021/5/13

89.90

165.20

110.30

188.08

2021/5/14

99.30

181.60

122.20

206.98

2021/5/14

98.20

185.10

125.00

209.54

2021/5/15

103.30

187.30

126.70

213.90

2021/5/16

103.31

187.23

126.89

213.84

2021/5/17

110.50

196.30

135.60

225.26

2021/5/18

117.20

199.80

135.40

231.64

2021/5/19

118.20

201.20

137.20

233.35

2021/5/20

116.00

201.20

138.50

232.24

2021/5/21

116.60

203.60

138.40

234.62

2021/5/22

117.50

204.40

139.20

235.77

2021/5/23

119.60

205.40

140.40

237.68

2021/5/24

122.80

207.50

141.50

241.11

2021/5/25

118.90

207.00

143.30

238.72

2021/5/27

124.80

209.70

143.60

244.03

2021/5/28

123.40

210.40

147.20

243.92

2021/5/29

121.70

210.80

144.00

243.41

2021/5/30

123.70

211.80

145.10

245.28

2021/5/31

123.70

212.90

145.60

246.23

2021/6/1

125.00

214.00

147.50

247.83

2021/6/5

127.50

217.30

150.60

251.94

2021/6/6

128.90

218.20

151.00

253.43

2021/6/7

129.50

217.60

151.40

253.22

2021/6/8

129.70

219.60

151.70

255.04

2021/6/9

129.30

219.30

151.70

254.58

2021/6/10

130.10

219.80

151.90

255.42

2021/6/11

128.10

218.80

153.40

253.54

2021/6/12

129.00

221.50

154.70

256.33

2021/6/13

127.70

221.30

152.60

255.50

2021/6/14

127.30

221.60

153.70

255.56

2021/6/15

130.50

224.50

152.70

259.67

2021/6/16

124.10

220.70

153.10

253.20

2021/6/17

124.90

221.80

153.60

254.55

2021/6/18

130.00

225.30

156.20

260.12

2021/6/19

132.70

226.70

155.60

262.68

2021/6/20

128.40

224.70

155.90

258.80

2021/6/21

132.00

224.60

154.20

260.52

2021/6/22

129.60

223.40

151.30

258.27

2021/6/23

128.90

224.60

155.30

258.96

2021/6/25

129.00

221.50

154.70

256.33

2021/6/26

127.60

224.70

153.40

258.40

2021/6/28

128.30

225.10

153.80

259.10

2021/7/2

136.70

229.20

155.00

266.87

2021/7/5

132.70

228.70

155.10

264.41

2021/7/7

129.00

228.50

156.20

262.40

2021/7/12

140.60

235.40

159.70

274.19

2021/7/14

136.00

235.70

161.30

272.12

2021/7/19

134.50

237.10

160.60

272.59

2021/7/21

135.40

240.10

163.60

275.65

2021/7/26

151.77

257.33

187.43

298.75

2021/7/30

154.50

265.30

194.70

307.01

2021/8/4

163.77

276.84

200.89

321.65

2021/8/6

161.64

278.79

201.86

322.26

2021/8/7

170.84

283.11

201.87

330.66

2021/8/9

171.30

284.30

208.30

331.92

2021/8/10

169.75

283.55

205.65

330.48

2021/8/16

176.50

295.50

216.60

344.20

2021/8/23

183.04

312.93

229.14

362.53

2021/8/31

201.46

329.37

240.37

386.10

2021/9/7

206.50

340.40

254.00

398.14

2021/9/13

212.80

350.00

257.20

409.61

表7-1的监测数据日期是2020年12月21日~2021年9月13日的,由表中数据可知,每次塌方发生,表面监测数据都突然增大,表明塌方引起边坡表面变形和发生了位移;监测数据多,已把中间数据省略。控制单响(孔)药量和合理设置孔间微差时间后,渐变段和基坑开挖爆破振动对边坡表面变形/位移影响很小。

7.2多点位移计监测

导流洞进口边坡设置了多个4点式位移计,用来监测边坡深度变形/位移情况,其中编号为M401-DLJ1多点位移计(型号SDW-100)的监测数据如下表所示。

表7-2      多点位移计M401-DLJ1监测简化数据表

观测日期

温度(℃)

相对位移计算成果(mm)

备注

1#

2#

3#

4#

锚头深度10m

锚头深度20m

锚头深度35m

锚头深度50m

2020/12/14

7.8

0.00

0.00

0.00

0.00

基准值

2020/12/26

7.9

-0.02

0.03

0.25

0.24

发生塌方

2020/12/27

2.6

0.04

0.11

0.35

0.07

2021/3/9

8.2

8.27

10.75

12.52

12.68

2021/3/11

8.4

8.73

11.30

12.60

13.45

发生塌方

2021/3/12

15.1

11.07

14.13

12.71

18.78

2021/3/13

8.7

11.85

16.63

19.56

19.24

2021/3/20

12.7

17.41

26.52

31.95

30.16

发生塌方

2021/3/21

10.2

18.81

28.92

34.82

32.81

2021/3/22

11.2

25.35

37.82

46.31

42.34

2021/3/23

8.2

26.55

40.01

49.35

44.53

2021/5/10

20.3

30.30

46.57

57.85

53.10

发生塌方

2021/5/11

18.6

30.93

46.59

58.08

54.03

2021/5/12

18.5

31.17

47.62

58.16

54.82

2021/5/13

18.3

31.51

47.82

58.19

55.47

2021/5/14

18.0

35.67

57.44

58.51

58.27

2021/5/14

19.8

36.40

58.14

58.50

58.58

2021/7/29

24.9

46.18

57.64

48.87

62.73

2021/8/2

23.1

47.51

57.59

48.85

62.84

2021/8/6

25.1

47.50

57.44

48.41

2021/8/30

19.4

49.74

57.36

39.80

2021/9/6

19

49.75

57.39

39.82

多点位移计M401-DLJ1监测的相对位移曲线见图7-1。

图7-1   导流洞进口边坡多点位移计M401-DLJ1相对位移过程线

由表中数据和监测的相对位移过程线可知,3月10日和5月10日两次塌方发生,表面监测数据都突然增大,表明塌方引起边坡深层变形和发生了位移;监测数据多,已把中间数据省略。控制单响(孔)药量和合理设置孔间微差时间后,渐变段和基坑开挖爆破振动对边坡深层变形/位移影响很小,边坡趋向安全稳定。

7.3锚索测力计监测

导流洞进口边坡设置了多个四弦式锚索测力计,用来监测边坡深度变形/位移情况,其中编号为PR03-DLJ锚索测力计(型号BGK4900-1000kN)的监测数据如下表所示。

表7-3  锚索测力计PR03-DLJ监测简化数据表

观测日期

温度(℃)

荷载(kN)

预应力损失率(%)

备注

2020/10/14

21.0

976.8

0.00

锁定值

2020/10/18

13.9

963.6

1.35

爆破开挖后

2020/10/19

16.5

963.1

1.40

2020/12/22

3.4

950.3

2.7

2020/12/26

8.0

948.3

2.9

塌方

2020/12/27

-1.0

946.8

3.1

2021/3/11

8.8

959.8

1.7

塌方

2021/3/12

17.6

1017.1

-4.1

加密观测

2021/3/13

17.6

1041.4

-6.6

加密观测

2021/3/21

8.0

1128.3

-15.5

加密观测

2021/3/22

4.1

1211.1

-24.0

加密观测

2021/3/23

5.3

1223.0

-25.2

加密观测

2021/5/11

14.9

1265.8

-29.6

塌方

2021/5/12

14.3

1269.1

-29.9

加密观测

2021/5/13

15.0

1271.6

-30.2

加密观测

2021/5/14

14.8

1316.9

-34.8

加密观测

2021/5/14

23.8

1322.1

-35.3

加密观测

2021/5/15

14.8

1329.8

-36.1

加密观测

2021/6/10

12.9

1369.6

-40.2

2021/6/11

15.0

1369.6

-40.2

2021/7/21

22.3

1380.6

-41.3

2021/7/26

24.0

1401.4

-43.5

2021/8/20

19.7

1448.1

-48.2

2021/8/23

16.2

1453.0

-48.7

2021/8/30

15.1

1456.4

-49.1

2021/9/6

15.0

1458.3

-49.3

锚索测力计PR03-DLJ监测荷载曲线见图7-2。

图7-2    锚索测力计PR03-DLJ监测荷载曲线

由表中数据和监测的荷载曲线可知,3月10日和5月10日两次塌方发生,表面监测数据都突然增大,塌方引起边坡变形导致荷载增加;监测数据多,已把中间数据省略。控制单响(孔)药量和合理设置孔间微差时间后,渐变段和基坑开挖爆破振动对边坡深层变形/位移影响很小,边坡趋向安全稳定。

截止2021年12月8日,监测量数据表明:导流洞进口边坡表面位移、岩石内部位移、锚杆应力及锚索测力计荷载变化均较小,边坡处于相对稳定状态。当然,边坡的安全稳定还有锚索等支护起了很大作用。

8结语

当边坡(物体)对爆破地震波敏感时,需要大大地降低最大单响(孔)装药量,尽可能减少爆破地震波对边坡(物体)的影响,使边坡(物体)安全稳定。

爆破振动常常采用萨道夫斯基经验公式:v=k(Q^(1/3)/R)^α对质点振动速度V值进行计算,结合物体表面观测和采用多点位移计、锚索测力计等监测手段,爆破振动监测会更准确!

参考文献

[1]赵东波.陈怀宇. 浅谈爆破振动的控制措施[J].工业安全与环保.2020,46(02): 63-66.

[2]庞海波.爆破振动有害效应的预防和控制[J]. 露天采矿技术. 2019,34(03): 22-24.

[3] 崔雪姣.周建敏.赵明生.余红兵.李杰.延时间隔对爆破振动信号时频特征的影响[J].工程爆破. 2020,26(03): 85-88.

[4] 孙崔源.薛里.孟海利.付天杰.康永全. 几种典型爆破振动控制技术的试验研究[J].北京理工大学学报. 2018,38(04):359-363+370.

[5] 于崇.岳好真.李海波.周传波.陈士海.邵珠山. 基于岩体质量的爆破控制参数及可靠度分析[J].岩土力学. 2021,42(08): 2239-2249.

1